News Local

West Oro residents fear potential water contamination 0

By Sara Carson, Orillia Packet & Times

Denis Paccagnella, Susan Woods, director of the West Oro Ratepayers’ Association (WORA), and Mark Scharf, a WORA adviser, stand at the proposed site of a TRY Recycling transfer and processing facility. WORA and Paccagnella are concerned operating the facility at the Line 7 site could impact water running underneath.
SARA ROSS - THE PACKET & TIMES

Denis Paccagnella, Susan Woods, director of the West Oro Ratepayers’ Association (WORA), and Mark Scharf, a WORA adviser, stand at the proposed site of a TRY Recycling transfer and processing facility. WORA and Paccagnella are concerned operating the facility at the Line 7 site could impact water running underneath. SARA ROSS - THE PACKET & TIMES

ORO-MEDONTE - 

A group of concerned Oro-Medonte residents are fighting to prevent TRY Recycling from operating in the township.

“It’s because of the water,” said Susan Woods, director of the West Oro Ratepayers’ Association (WORA). “It’s the drinking water for so many of us downstream.”

TRY Recycling has been working toward operating a recycling transfer and processing facility on 62 acres at Line 7 and Old Barrie Road since 2009.

The London-based company, in operation since 1991, takes solid, non-hazardous waste — such as material from construction sites — and recycles them into salable new products.

They submitted an application for a certificate of approval from the Ministry of the Environment (MOE) in January 2011.

WORA members — made up of 300 families — have spent $40,000 seeking legal advice to fight the application and to hire consultants to review TRY Recycling’s reports, conducted by Golder Associates.

WORA hired Ken Howard, a university professor and groundwater consultant. He concluded his report in June 2012.

“(Howard) says (the Golder) report is flawed and this is a dangerous spot,” said Mark Scharf with WORA. “We’re only 45 feet above an aquifer and this has got sandy, porous soil here, so any pollutants can get into that aquifer fairly quickly.”

Howard noted the Golder report didn’t include an aquifer vulnerability assessment, “which, if conducted, would certainly indicate that shallow groundwater beneath the Oro Moraine (and particularly beneath the site), to be highly susceptible to pollution from surface sources.”

Howard also found the close proximity of the water table to the quarry floor would provide little, if any, opportunity for contaminants to be attenuated.

The proposed site — on the edge of the Oro Moraine — is an old quarry, currently being used as a township work site.

Jim Graham, TRY Recycling’s CEO, said WORA’s reports review only the company’s preliminary studies.

“These reports were based on our initial submission (to the MoE),” he said. “The ministry reviews our preliminary studies and would have reviewed these comments to them.”

The ministry then asked for additional information and studies, Graham said.

Woods said WORA wasn’t informed of the updated testing.

“I don’t know that his updated reports had been shared with us,” she said. “It would be helpful to have that shared widely.”

Testing to date — done by Golder Associates — has concluded what the company had believed all along, Graham said.

“For the types of materials we’re going to be diverting, we won’t have any negative impact on the environment, on the water, or any other aspect,” he said. “That’s something we were very careful about in site selection before we even began.”

All the materials collected will be solid and non-hazardous.

“Residents looking at it from a technical point of view should be very satisfied that we’ve done our due diligence and proven all our original assumptions,” Graham said.

In 2012, three Oro-Medonte residents appealed to the Ontario Municipal Board (OMB) expressing concerns about planned zoning amendments that would allow the facility to be built on a corner of the Oro Moraine.

In March, the OMB concluded “this was a use that was permitted on the site and that the applicants against could voice a lot of their concerns through the certificate-of-approval process,” Graham said.

No specific environmental measures are required on the site.

“We settled to take it to the MoE,” said Denis Paccagnella, one of the appellants.

TRY Recycling is hoping to get its certificate of property use at the beginning of next year.

The certificate will manage all aspects of the operation, including air, noise, storm water along with what types of material can be taken in, the equipment used to process and more.

Once the certificate is obtained, TRY Recycling will have to submit a site plan to the township.

“From what we’ve seen so far, there are no red flags popping up, but keep in mind there is still testing to be completed,” Mayor Harry Hughes said. “They’re continuing to proceed on the basis that things are looking positive.”

Oro-Medonte must be satisfied by the Golder testing results — testing is still underway — to approve the operation.

“... We need the assurance there won't be a negative impact on the ground water,” Hughes said.

Along with the groundwater, WORA is concerned at the life of Oro-Medonte Site 11 landfill, Scharf said.

In January, Hughes told The Packet, under the current diversion rate, Site 11 has a life-span of seven years before it reaches capacity.

In the first year, TRY Recycling is expecting to divert at least 50,000 tonnes of materials from local landfills.

“We've requested we have the flexibility to receive materials and send materials out to all of Ontario, like we do with all of our sites, but 95% of the material that comes in is coming within an hours drive,” Graham said.

A portion of what's brought in cannot be recycled.

“And it's going to go to our dump down the road,” Scharf said.

Graham said this is not the case.

“We identified landfills throughout Ontario that those non-recycled materials can go to,” he said, adding this does include Site 11.

Every year, TRY Recycling must note how much material they didn't recycle and where it went, Graham said.

The site will house a scale house and office, tipping areas throughout site, processing areas, final process areas and residential and commercial drop off areas.

It will take about 60 days to construct the entire site, Graham said.

Initially, the company is expecting to hire 15 people.

“Our current facilities in London have 50 people employed and we would like to see it ramp up to that in three to five years,” Graham said.

They will be hiring heavy equipment operators, site managers and general labourers.

“We're looking at this to be a long-term investment that's going to provide significant environmental jobs,” Graham said.

sara.ross@sunmedia.ca

Twitter: @Sara_VRoss

 

 

 

Reader's comments »

By adding a comment on the site, you accept our terms and conditions and our netiquette rules.


Featured Businesses

Go to the Marketplace »